Message from the Dean

Dean Kingsford

The move from PH3 into "new" offices and labs for the next three years has been wonderfully accommodated by everyone. I particularly recognize that this was not easy and required many sacrifices. Thank you all for your hard work and "get-it-done" attitude. Everyone's hard work is making this new building a reality.

The project is moving along according to schedule, and preparations for the hazmat are well underway. This web page will be added to regularly as new information about the project is available. Continue to check this site for updates and details about the project, including what is being done to mitigate exposure to the dust and other potential hazards.

- Dean Kingsford

Latest Updates: 6/4/08

Updates on Utility Shutdowns - Status Report from Mark Zakhour, Senior Construction Manager

  • Electrical Shutdown: Saturday, 6/7/08, 7:30 am - 5:00 pm, Microbiology Building
  • Water Shutdown: Saturday, 6/14/08, 7:00 am – 5:00 pm, MLSC, FO4-FO5, and FA3
  • Gas Shutdown: Saturday, 6/14/08, 7:00 am – 5:00 pm, Microbiology
  • Hard demolition of building scheduled to begin during the week of 6/16/08
  • Contractor fenced the remainder of Parking Lot 8 on June 2.
  • East Campus Drive to one lane during outages. Flagmen to be provided.
  • North end of Microbiology building work to begin:
    1. relocation of fire department standpipe system
    2. installation of footings and steel columns to support Micro decks.

PH3 Construction Contacts

Please do NOT contact Hunt Construction Group directly.